STATUS OF OPEN ACCESS CUSTOMERS AS ON DATED 21.07.2010
Detail of the Open Access customer-Long term
|
|
Sr. No.
|
Date of receipt of application
|
Name of the Open Access Customer
|
Point(s) of injection
|
Points(s) of drawl
|
Open Access capacity allowed (MW)
|
Period of the access granted
|
Actual utilization in MU
|
|
Start date
|
End Date
|
|
1.
|
18.10.07
|
M/s Reliance Industries Ltd.
|
HVPNL Interface at Jhajjar
|
Yet to be decided by RIL
|
500
|
Under process
|
Under process
|
No further response from RIL after results of preliminary load flow studies intimated to them (probably consumer is no longer interested)
|
|
2.
|
03.08.09
|
M/s Shahabad Sugar Co-Operation Ltd.
|
Shahabad Sugar Co-Operation Ltd.
|
HPPC
|
24
|
04-01-2010
|
Long- term
|
Open access allowed. Transaction under Process
|
|
3.
|
01.09.09
|
DLF Utilities LTD
|
Yet to be decided
|
Yet to be decided
|
12
|
Under process
|
Under process
|
Connectivity allowed subject to signing of connection agreement
|
|
4.
|
01.09.09
|
DLF Utilities LTD
|
Yet to be decided
|
Yet to be decided
|
32
|
Under process
|
Under process
|
Connectivity allowed subject to signing of connection agreement
|
|
5
|
25.03.10
|
M/S NVVN
|
Yet to be decided
|
Yet to be decided
|
5
|
Under process
|
Under process
|
Comfort letter given. NVVN to take further action through HAREDA
|
|
6
|
04.05.10
|
M/s Gemco Energy Ltd Bhiwani
|
Yet to be decided
|
Yet to be decided
|
15
|
Under process
|
Under process
|
Planning wing has been requested for system studies on 05.05.10. Response from planning wing is awaited
|
|
Detail of the Open Access customer-Short term
|
|
Sr. No.
|
Date of receipt of application
|
Name of the Open Access Customer
|
Point(s) of injection
|
Points(s) of drawal
|
Open Access capacity allowed (MW)
|
Period of the access granted
|
Actual utilization in MU
|
|
Start date
|
End Date
|
|
1.
|
19.01.08
|
M/s Jindal Stainless Ltd. Hisser (Haryana)
|
400/220 KV OPTCL Grid Sub Station Duburi New
|
Inter connection of Haryana transmission system with JSL Sub Station,Hissar
|
60
|
01-02-08
|
29-02-08
|
Rejected by SLDC Orrisa
|
|
2.
|
04.01.08
|
M/S RICO Auto Ind.Ltd.
|
132KV Bus of GSS industrial Area,Kota,Sub -Station
|
66KV Bus at Badsahpur Gurgoan Sub Station of HVPNL
|
9
|
01-04-08
|
31-03-09
|
Cancelled due to payment default
|
|
3.
|
18.02.08
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generat-ing station at generator bus bar
|
Inter connection of HVPNL Grid With generat-ing station at generator bus bar
|
4
|
20-02-08
|
31-03-08
|
Transaction Concluded
|
|
4.
|
19.06.08
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3
|
01-07-08
|
31-07-08
|
Transaction Concluded
|
|
5.
|
21.08.08
|
M/s Jindal Stainless Ltd. Hisser (Haryana)
|
JSL Orrisa
|
JSL Haryana Station, Hissar
|
75
|
1.09.2008
|
30.09.08
|
Rejected by SLDC Orrisa
|
|
6.
|
20.06.08
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3.5
|
1.09.2008
|
30.09.08
|
Transaction Concluded
|
|
7
|
29.09.08
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3.5
|
3.10.2008
|
31.10.08
|
Transaction Concluded
|
|
8
|
31.10.08
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3.5
|
1-11-08
2-11-08
3-11-08
4-11-08
5-11-08
14-11-08
|
1-11-08
2-11-08
3-11-08
4-11-08
9-11-08
24-11-08
|
Transaction Concluded
|
|
9
|
07.12.08
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3.5
|
12-12-08
|
31-12-08
|
Transaction Concluded
|
|
10
|
24.12.08
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3.5
2.0
3.5
|
02-01-09
24-01-09
27-01-09
|
23-01-09
26-01-09
31-01-09
|
Transaction
Concluded
|
|
11
|
23.01.09
|
M/s Adani Enterprises Ltd.
|
Interconnection of HVPNL Grid With generating stn at generator bus bar
|
Noida Power Company (UP)
|
3.5
2.0
3.5
2.0
3.5
|
01-02-09
14-02-09
16-02-09
20-02-09
23-02-09
|
13-02-0915-02-0919-02-0922-02-0928-02-09
|
Transaction
Concluded
|
|
12
|
24.02.09
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3.5
2.0
3.5
|
01-03-09
06-03-09
11-03-09
|
05-03-09
10-03-09
31-03-09
|
Transaction
Concluded
|
|
13
|
16.02.09
|
M/s Jindal Stainless Ltd. Hisser (Haryana)
|
400/220 KV OPTCL Grid Sub Station Duburi New
|
Inter connection of Haryana transmission system with JSL Sub Station, Hissar
|
75
|
01-03-09
|
31-05-09
|
Rejected by SLDC Orrisa
|
|
14
|
20.03.09
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3.5
2.0
3.5
|
01-04-09
10-04-09
13-04-09
|
09-04-09
12-04-09
30-04-09
|
Transaction
Concluded
|
|
15
|
13.03.09
|
M/S Grasim Industries Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Yet to be finalized
|
Up to 7 MW
|
01-04-09
|
31-03-10
|
Allowed connectivity. Subsequentlywithdrawn by M/S Grasim Industries Ltd.
|
|
16
|
29.04.09
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3.5
2.0
3.5
|
04-05-09
08-05-09
11-05-09
|
07-05-09
10-05-09
31-05-09
|
Transaction
Concluded
|
|
17
|
14.05.09
|
M/s Jindal Stainless Ltd. Hisser (Haryana)
|
132 KV Grid Sub Station HVPNL
|
Yet to be finalised
|
25
|
01-08-09
|
31-12-09
|
Approval given on 31.07.09. Customer did not established connectivity of its own.
|
|
18
|
30.05.09
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generat-ing station at generator bus bar
|
Noida Power Company (UP)
|
3.5
2.0
3.5
|
01-06-09
11-06-09
15-06-09
|
10-06-09
14-06-09
30-06-09
|
Transaction
Concluded
|
|
19
|
01.06.09
|
M/s Adani Enterprises Ltd.
|
Inter connect-ion of HVPNL Grid With gen-erating station at Generator bus bar
|
Power Company (UP)
|
3.5
|
02-06-09
|
02-06-09
|
Transaction
Concluded
|
|
20
|
09.07.09
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
Noida Power Company (UP)
|
3
|
10-07-09
|
10-07-09
|
Transaction Concluded
|
|
21
|
10.07.09
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Noida Power Company (UP)
|
3
|
11-07-09
|
11-07-09
|
TransactionConcluded
|
|
22
|
10.07.09
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
Noida Power Company (UP)
|
3
|
13-07-09
|
13-07-09
|
Transaction
Concluded
|
|
23
|
09.07.09
|
M/s Adani Enterprises Ltd.
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
Noida Power Company (UP)
|
3
|
14-07-09
|
31-07-09
|
Transaction
Concluded
|
|
24
|
01.07.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generat-ing station at
generator bus bar
|
Up to 7MW
|
04-07-09
|
31-07-09
|
Transaction
Concluded
|
|
25
|
07.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Interconnection of HVPNL Grid With gen-erating stn at
Gen bus bar
|
4MW
|
08-08-09
|
08-08-09
|
Transaction
Concluded
|
|
26
|
08.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With genera-ting station at
generator bus bar
|
5MW
|
09-08-09
|
09-08-09
|
Transaction
Concluded
|
|
27
|
09.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connect-ion of HVPNL Grid With generating station at
Generator bus bar
|
5MW
|
10-08-09
|
10-08-09
|
Transaction
Concluded
|
|
28
|
10.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
5MW
|
11-08-09
|
11-08-09
|
Transaction
Concluded
|
|
29
|
11.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
5MW
|
12-08-09
|
12-08-09
|
Transaction
Concluded
|
|
30.
|
23.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
4MW
|
24-08-09
|
24-08-09
|
Transaction
Concluded
|
|
31
|
24.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Tax tile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
4MW
|
25-08-09
|
25-08-09
|
Transaction
Concluded
|
|
32.
|
25.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
4MW
|
26-08-09
|
26-08-09
|
Transaction
Concluded
|
|
33.
|
26.08.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
4MW
|
27-08-09
|
27-08-09
|
Transaction
Concluded
|
|
34.
|
31.08.09
|
M/s Mittal
processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
5MW
|
01-09-09
|
30-09-09
|
Transaction
Concluded
|
|
35.
|
02.10.09
|
M/s Mittal rocessor Pvt. Ltd.
|
Grasim hiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
4MW
|
03-10-09
|
15-10-09
|
Transaction
Concluded
|
|
36.
|
15.10.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
5MW
|
16-10-09
|
16-10-09
|
Transaction
Concluded
|
|
37.
|
15.10.09
|
M/s Mittal processor Pvt. Ltd.
|
Grasim Bhiwani Taxtile Ltd
|
Inter connection of HVPNL Grid With generating station at
generator bus bar
|
5MW
|
17-10-09
|
17-10-09
|
Transaction
Concluded
|
|
38
|
10.09.09
|
M/s Golden Terry towel ltd
|
Yet to be finalized
|
33KV Golden Terry towel ltd T/F
|
2MW
|
Yet to be finalized
|
Yet to be finalized
|
Approval given on 31.12.09
Connectivity
under process
|
|
39
|
17.09.09
|
M/s Nuchem Ltd
|
132KV Substation Tohana
|
Yet to be finalized
|
Upto 4MW
|
Yet to be finalized
|
Yet to be finalized
|
Approval given on 31.12.09
SEM to be installed by the customer
|
|
40
|
09.09.09
|
M/s JSL Ltd
|
Regional boundary of NR
|
JSL,HISSAR
|
Upto
50MW
|
15-09-09
|
15-12-09
|
Transaction
concluded
|
|
41
|
05.11.09
|
M/s DCM Textiles
|
Yet to be finalized
|
33 KV HTM Substation, Hisser
|
5.5MW
|
Yet to be finalized
|
Yet to be finalized
|
Approval given on 31.12.09.
SEM to be installed by the customer
|
|
42
|
04.11.09
|
M/S Grasim Industries Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Regional boundary of NR
|
2 MW
|
04-11-09
|
31-12-09
|
Transaction
concluded
|
|
43
|
06.01.10
|
M/s Star Wire India Ltd., Ballabgarh, Faridabad
|
Regional boundary of NR
|
66 kV, Globe Steel Substation, Ballabhgarh
|
3MW
|
07-01-10
|
31-03-10
|
Transaction
concluded
|
|
44
|
02.12.09
|
M/s Mittal Processor Pvt. Ltd.,(Textile Division), Panipat
|
Yet to be decided
|
33 kV S/stn at M/s Mittal Processor Pvt. Ltd, Sec-29, Panipat
|
1.5 MW
|
Yet to be decided
|
Yet to be decided
|
Not allowed by UHBVN as connection to the customer was yet to be released.
|
|
45
|
31.12.09
|
M/s JSL Ltd
|
Regional boundary of NR
|
JSL,HISSAR
|
Upto
75MW
|
16-12-09
|
15-03-10
|
Transaction
concluded
|
|
46
|
30.12.09
|
M/S Grasim bhiwani Textiles Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Regional boundary of NR
|
2 MW
|
01-01-10
|
31-03-10
|
Transaction
concluded
|
|
47
|
28.01.10
|
M/s BILT Power Ltd Yamunanagar
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Regional boundary of NR
|
4 MW
|
01-02-10
|
30-04-10
|
Transaction
concluded
|
|
48
|
02.02.10
|
M/s Sun Star overseas Ltd Sonipat
|
Yet to be finalised
|
M/s Sun Star overseas Ltd Sonipat
|
2.5 MW
|
Yet to be finalised
|
Yet to be finalised
|
Rejected by UHBVNL
|
|
49
|
22.02.10
|
M/s JSL Ltd
|
Regional boundary of NR
|
JSL,HISSAR
|
Upto
75MW
|
16-03-10
|
15-06-10
|
Transaction
concluded
|
|
50
|
10.03.10
|
M/S RICO Auto Ind.Ltd.
|
Regional boundary of NR
|
66KV Bus at Badsahpur Gurgoan Sub Station of HVPNL
|
15
|
01.04.10
|
30.03.11
|
Transaction
in process
|
|
51
|
05.04.10
|
M/S Grasim Industries Ltd.
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Regional boundary of NR
|
7 MW
|
05.04.10
|
30.06.10
|
Transaction in process
|
|
52
|
30.03.10
|
M/s Star Wire India Ltd., Ballabgarh, Faridabad
|
Regional boundary of NR
|
66 kV, Globe Steel Substation, Ballabgarh
|
3 MW
|
06-04-10
|
30-06-10
|
Transaction in process
|
|
53
|
08.04.10
|
M/s Napcon Turbo-chargers Pvt. Ltd.
|
Yet to be finalized
|
Yet to be finalized
|
1.5MW
|
Yet to be finalized by customer
|
Yet to be finalized by customer
|
Approval given on 28.04.10
SEM to be installed by the customer
|
|
54
|
07.04.10
|
M/S Laser Shaving Products Pvt. Ltd
|
Regional boundary of NR
|
M/S Laser Shaving Products Pvt. Ltd
|
6MW
|
01-05-10
|
31-07-10
|
Transaction Under process
|
|
55
|
04.05.10
|
M/s Oswal Global (Pvt.) Ltd,Faridabad
|
Regional boundary of NR
|
M/s Oswal Global (Pvt.) Ltd,Faridabad
|
1.6MW
|
25-05-10
|
24-08-11
|
Approval given on 04.06.10
SEM to be installed by the customer
|
|
56
|
14.05.10
|
M/s BSL Casting (P) Ltd. Faridabad
|
Regional boundary of NR
|
M/s BSL Pvt Ltd
|
2 MW
|
25-05-10
|
28-08-10
|
Transaction in process
|
|
57
|
14.05.10
|
M/s G.L.S. Industries Pvt. Ltd Gurgaon
|
Regional boundary of NR
|
M/s G.L.S. Industries pvt. Ltd
|
1.8MW
|
01-06-10
|
31-05-11
|
Approval given on 16.06.10 SEM to be installed by the customer
|
|
58
|
15.05.10
|
M/s JSL Ltd, Hissar
|
Regional boundary of NR
|
JSL,HISSAR
|
Upto
75MW
|
16-06-10
|
15-09-10
|
Withdrawn by applicant
|
|
59
|
11.05.10
|
M/s Punjab General Industries Pvt. Ltd., Faridabad
|
Regional boundary of NR
|
M/s Punjab General Industries Pvt. Ltd., Faridabad
|
4MW
|
01.06.10
|
31.05.11
|
Approval given on 03.06.10 SEM to be installed by the customer
|
|
60
|
27.04.10
|
M/s BILT Power Ltd Yamunanagar
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Regional boundary of NR
|
4 MW
|
08-05-10
|
31-07-10
|
Transaction
In process
|
|
61
|
31.05.10
|
M/s JSL Ltd, Hissar
|
Regional boundary of NR
|
JSL,HISSAR
|
Upto
100MW
|
16-06-10
|
15-09-10
|
Transaction in process
|
|
62
|
01.06.10
|
M/s SSA International, Panipat
|
Yet to be finalized
|
SSA International, Panipat
|
Upto 2 MW
|
Yet to be decided
|
Yet to be decided
|
Approval received from DISCOM and TS. Undertaking from customer awaited.
|
|
63
|
24.05.10
|
M/s Mann Feeds Pvt. Ltd, Faridabad
|
Regional boundary of NR
|
M/s Mann Feeds Pvt. Ltd, Faridabad
|
Upto 1.5 MW
|
Yet to be decided by customer
|
Yet to be decided by customer
|
Approval given on 05.07.10, SEM to be installed by the customer
|
|
64
|
07.06.10
|
M/s Hindustan Everest Tools Ltd Sonepat
|
Regional boundary of NR
|
M/s Hindustan Everest Tools Ltd Sonepat
|
Upto 2.5 MW
|
Yet to be decided
|
Yet to be decided
|
Approval received from DISCOM and TS. Undertaking from customer awaited.
|
|
65
|
07.06.10
|
M/s Star Wire India Ltd., Ballabgarh, Faridabad
|
Regional boundary of NR
|
66 kV, Globe Steel Substation, Ballabgarh
|
3 MW
|
01-07- 2010
|
30-09-2010
|
Transaction
In operation
|
|
66
|
09.06.10
|
M/S Grasim Industries Ltd., Bhiwani
|
Inter connection of HVPNL Grid With generating station at generator bus bar
|
Regional boundary of NR
|
7 MW
|
01.07.10
|
30.09.10
|
Transaction
In operation
|
|
67
|
10.06.10
|
M/s Golden Apparel Export Pvt. Ltd., Panipat
|
Power Exchange India through Mittal Processors Pvt. Ltd.
|
M/s Golden Apparel Export Pvt. Ltd., Panipat
|
1.2 MW
|
Yet to be decided
|
Yet to be decided
|
Application Under process. Consent from UHBVN awaited
|
|
68.
|
18.06.10
|
M/s Munjal Showa Ltd., Gurgaon
|
Indian Energy Exchange Ltd
|
M/s Munjal Showa Ltd., Gurgaon
|
3 MW
|
Yet to be decided
|
Yet to be decided
|
Consent from DHBVN awaited
|
|
69.
|
21.06.10
|
M/s SPL Industries Ltd., Faridabad
|
Indian Energy Exchange Ltd
|
M/s SPL Industries Ltd., Faridabad
|
1.5 MW
|
20.06.10
|
19.06.11
|
Approval given on 21.07.10, SEM to be installed by the customer
|
|
70.
|
24.06.10
|
M/s Bhupindra Steels (P) Ltd., Faridabad
|
Indian Energy Exchange Ltd
|
M/s Bhupindra Steels (P) Ltd., Faridabad
|
2 MW
|
07.06.10
|
07.06.11
|
Approval given on 21.07.10, SEM to be installed by the customer
|
|
71.
|
09.06.10
|
M/s Alchem International Ltd., Faridabad
|
Indian Energy Exchange Ltd
|
M/s Alchem International Ltd., Faridabad
|
3 MW
|
01.07.10
|
30.06.11
|
Approval given on 21.07.10, SEM to be installed by the customer
|
|
72
|
24.06.10
|
M/s Jotindra Steel and Tubes Ltd., Faridababd
|
Indian Energy Exchange Ltd
|
M/s Jotindra Steel and Tubes Ltd., Faridababd
|
2 MW
|
01.07.10
|
30.06.11
|
|
|
73
|
05.07.10
|
M/s Grasim Bhiwani Textiles Ltd.,
Unit Elegent Spinners,
Bhiwani
|
Regional boundary of NR
|
M/s Grasim Bhiwani Textiles Ltd.,
Unit Elegent Spinners, Bhiwani
|
2.9 MW
|
01.07.10
|
31.03.11
|
Consent from DHBVN and TS wing awaited
|
|
74
|
05.07.10
|
M/s Grasim Bhiwani Textiles Ltd.,
Unit Bhiwani Textile Mill, Bhiwani
|
Regional boundary of NR
|
M/s Grasim Bhiwani Textiles Ltd.,
Unit Bhiwani Textile Mill, Bhiwani
|
4.40 MW
|
01.07.10
|
31.03.11
|
Consent from DHBVN and TS wing awaited
|
|
75
|
05.07.10
|
M/s India Yamaha Motors Pvt. Ltd., Faridabad
|
Regional boundary of NR
|
M/s India Yamaha Motors Pvt. Ltd., Faridabad
|
5 MW
|
01.07.10
|
30.06.11
|
Consent from DHBVN and TS wing awaited
|
|
76
|
05.07.10
|
M/s REI Agro Ltd., Bawal
|
Regional boundary of NR
|
M/s REI Agro Ltd., Bawal
|
3.2
|
01.07.10
|
30.09.10
|
Consent from DHBVN and TS wing awaited
|
|
77.
|
19.07.10
|
M/s RICO Auto Ltd.
|
Regional boundary of NR
|
M/s RICO Auto Ltd.
|
15
|
01.08.10
|
30.10.10
|
Application under process
|