ACHIEVEMENTS
........... SINCE MARCH 2005 TO June 2010.
From March 2005 to June 2010, total 208 new substations were commissioned, 400 existing substations augmentedand 2733.363 Km transmission lines constructed by adding 10072.2 MVA transmission capacity with an investment of Rs. 1964.8 crore. Details of works are given at Annexure ‘A’ & ‘B’.
Table showing the new Substations/Augmentations and new Lines constructed from March 2005 to June 2010.
|
Sr. No.
|
ITEM
|
Number
|
Cost
(Rs. In crores)
|
|
1.
|
New Sub-stations
|
400kV
|
1
|
103.00
|
| |
|
220kV
|
8
|
185.52
|
|
|
|
132kV
|
36
|
263.40
|
|
|
|
66kV
|
23
|
123.96
|
|
|
|
33kV
|
140
|
182.53
|
|
|
|
Total
|
208
|
858.41
|
|
2.
|
Augmentations
|
220kV
|
39
|
130.74
|
|
|
|
132kV
|
88
|
186.10
|
|
|
|
66kV
|
72
|
147.57
|
|
|
|
33kV
|
200
|
89.07
|
|
|
|
Total
|
400
|
553.48
|
|
3.
|
New lines (in KMs)
|
400kV
|
48.100
|
54.77
|
|
|
|
220kV
|
731.170
|
216.32
|
|
|
|
132kV
|
574.235
|
155.88
|
|
|
|
66kV
|
289.752
|
62.33
|
|
|
|
33kV
|
1090.106
|
63.61
|
|
|
|
Total
|
2733.363
|
552.91
|
|
|
G. Total
|
|
|
1964.80
|
|